The Revolutionary FAR Overhaul (RFO) moved several clauses that show up in almost every defense subcontract to new numbers. The cybersecurity clauses moved out of the 52.204 series into a new 52.240 series, and DoD moved its assessment clause into a new DFARS Part 240. Here is what changed, what didn't, and what is still only a proposal.

Confirmed changes

These are in effect through class deviations. DoD's took effect February 1, 2026. Contracts awarded before an agency's deviation keep the old numbers until they're modified, so you may see both numbers in the same supply chain for a while.

Old numberNew numberWhat changed
FAR 52.204-21, Basic SafeguardingFAR 52.240-93Number only. Same 15 requirements and same flowdown; still excludes COTS items.
FAR 52.204-23 (Kaspersky), 52.204-25 (Section 889), 52.204-30 (FASCSA orders)FAR 52.240-91, Security Prohibitions and ExclusionsThree clauses combined into one. A single written report within 72 hours replaces the separate reporting windows. Flows down to all subcontracts, including commercial ones.
FAR 52.204-24, 52.204-26 and related representationsFAR 52.240-90Representations and certifications consolidated into one provision.
DFARS 252.204-7019EliminatedThe standalone requirement to post a basic NIST SP 800-171 self-assessment score before award is gone.
DFARS 252.204-7020DFARS 252.240-7997Renumbered. DoD assessment access remains; the basic self-assessment requirement was removed.

Unchanged

DFARS 252.204-7012 (safeguarding covered defense information and 72-hour cyber incident reporting) and DFARS 252.204-7021 (CMMC) kept their numbers. FAR 52.244-6, the list of clauses primes must flow down to commercial suppliers, is still 52.244-6.

Proposed, not final

The FAR Council has proposed moving every clause in FAR subpart 52.2 to a new 52.4 series. If adopted, clause numbers across the whole FAR would start with 52.4 instead of 52.2.

A June 2026 proposed rule would consolidate FAR 52.204-12 (Unique Entity Identifier maintenance) and 52.204-18 (CAGE code maintenance) into a revised 52.204-13.

The same overhaul proposes renaming "federal contract information" to "covered federal information." Until these are final, the current numbers and terms still apply.

What to do with your POs

Match the clause set to the prime contract's award date. Your obligations come from the clauses and dates in your own documents, not from what the buyer's template assumes.

If a new PO still cites DFARS 252.204-7019, ask the buyer which clause in the prime contract requires it.

Update your own flowdown templates and compliance checklists so they carry both the old and new numbers until your older contracts close out.

Sources

Last checked November 19, 2026. Educational content from a working contracts professional, not legal advice.