These two clauses show up together in a lot of POs, but they protect different information at very different levels of effort. The short version: 52.204-21 is basic hygiene for federal contract information. 7012 is full NIST SP 800-171 for covered defense information, plus 72-hour incident reporting.

Side by side

FAR 52.204-21 (now 52.240-93)DFARS 252.204-7012
ProtectsFederal contract information (FCI)Covered defense information (CDI), a kind of CUI
Requires15 basic safeguarding requirementsNIST SP 800-171, 72-hour incident reporting to DoD, 90-day image retention, FedRAMP Moderate-equivalent cloud
CMMC levelLevel 1Level 2
Flows downWhere the sub may have FCI; not for COTS itemsWhere performance involves CDI or operationally critical support
2026 overhaulRenumbered to 52.240-93Unchanged

How to tell which you need

If you only receive purchase orders, drawings without CUI markings and ordinary contract correspondence, you're probably handling FCI, and 52.204-21 is the clause that matters.

If the prime will send controlled technical data or other marked CUI, 7012 applies, and so does the much bigger effort that comes with it.

Ask the buyer in writing whether any CDI will be shared under the PO. If none will, ask them to drop 7012 or make it conditional on CDI being provided.

Sources

Last checked November 19, 2026. Educational content from a working contracts professional, not legal advice.